Rep. Chung Il-young, a member of the National Assembly Land, Infrastructure and Transport Committee, demanded that the 7th airport development master plan, to be released in November, be required to reflect the fifth phase expansion of Incheon International Airport.
Rep. Chung made the remarks while speaking at a parliamentary interpellation of the MOLIT on Oct. 22.
The fifth phase expansion of Incheon International Airport calls for an investment of approximately 6 trillion won with a focus on building a fifth runway and a third passenger terminal.
If the expansion project is completed, the airport is predicted to see its annual passenger accommodation capability and aircraft flight handling capability surge to 131 million people and 830,000 flights.
Rep. Chung called for a review on the basis and feasibility of the project’s demand forecasting, saying that a delay in the passenger capability saturation point of the airport from 2033 to 2038 will be considered by studying the opening of new regional airports.
According to data submitted by Incheon International Airport Corp., 87.7 percent of domestic passengers using Incheon International Airport came from the Seoul metropolitan and central region areas.
Rep. Chung said that current demand, moving to new regional airports and new flight demand need to be separated, and demand forecasting should reflect factors such as the possible delay of the opening of new airports.
He pointed out that, in the past, there was a huge difference between demand prediction for Incheon International Airport and actual passenger demand.
One forecast, made in 2012 based on data released by Incheon International Airport, showed that passengers would total about 53.1 million in 2019, but the actual number of users stood at approximately 71 million, over 33.7 percent more than predicted.
Incheon International Airport saw the number of passengers surpass 54 million won in 2016 and 2017, even before the opening of its second passenger terminal, causing facility crowding and operational bottlenecks.
Rep. Chung maintained that the government has to consider the fact that the fifth phase project would last about eight years.
The first passenger terminal is to be renovated between 2028 and 2035, while the fourth and third runway are to undergo a renewal between 2031 and 2032 and between 2032 and 2033, respectively.
Rep. Chung demanded that the direction and schedule of the implementing of the fifth phase project in accordance with the 7th airport development master plan between 2026 and 2030 need to be clarified on top of MOLIT and Incheon International Airport Corp.’s construction schedule of each stage and other factors.
“In the past, Incheon International Airport had suffered facility shortage and crowd since the actual passenger outnumbered prediction, and as it is too late to cope with expansion the crowding of airports, so they are required to make preparations with demand forecasting from a long-term perspective,” he said.
Rep. Chung Calls for Stronger Safety Management at Construction Sites
Rep. Chung Il-young, a member of the National Assembly Land, Infrastructure and Transport Committee, said data submitted by the Ministry of Land, Infrastructure and Transport (MOLIT) showed that the top 10 contractors on the 2026 construction capability evaluation list saw defect review receipt cases stand at more than 5,000 for the recent four years and six months.
This indicates that, as accidents that cause deaths are on a constant rise at construction sites, the top construction companies are required to ramp quality and safety management responsibility.
According to Rep. Chung of the Democratic Party, figures presented by MOLIT showed that the number of defect review receipt cases for the top 10 construction companies stood at 5,279.
By contractor, Daewoo E&C topped the defect review application list with 1,060 cases, followed by Hyundai E&C with 1,034 cases, HDC Hyundai Development Company with 738 cases, Lotte E&C with 723 cases and POSCO E&C with 630 cases.
In particular, 2,132 cases, or 40.4 percent of the total, had been scrutinizing as of June.
Even though the receipt of defect review applications means the scrutiny of most of the defect review applications has not yet been finished and the reason for the delay needs to be examined.